We finished putting down the flooring last week and the lines today (January 15, 2020). Praise God for all that He has done and for providing us with the funds, materials, donations, and labor to complete this project. A few small details left to go, but we are all set to use this new building at camp this weekend.
If you haven't signed up yet, our first of two snow camps kicks off this Friday. Come hear the Word of God preached, enjoy the snow, go swimming, and play in our new Multipurpose Center.
Information regarding the dedication ceremony for the Multipurpose Center will be posted soon. We'll be dedicating this new building to the Lord and sharing about our plans for the next phase of this project. Now that Phase 1 is complete, we'd like to add on restrooms, a lobby and a canteen to the east side of the building.
In Christ,
Mike Crase